Build a project grid with a real scheduling engine underneath it. Stack: your choice, Postgres, Docker Compose. This is a computation problem more than a UI problem; budget accordingly. Sheet model: rows with typed columns (text, number, date, contact, dropdown, checkbox, duration, predecessors), and rows that nest — indenting a row makes it a child of the row above. Parent rows compute rather than store: start is the earliest child start, finish is the latest child finish, duration follows, and percent complete is the duration-weighted mean of children. A parent's dates are never directly editable. The scheduling engine: - Predecessors are typed: finish-to-start, start-to-start, finish-to-finish, start-to-finish, each with an optional lag in working days, positive or negative. - A working-day calendar with configurable weekends and a holiday list. All durations and lags are in working days. - Changing any date or duration triggers a forward pass to recompute every downstream row, then a backward pass to compute float. Rows with zero float are the critical path and are highlighted. - Circular dependencies are detected and refused at the point of creation, naming the cycle. Do not let a cycle be saved and discovered at recompute time. Gantt view beside the grid, sharing scroll, with dependency arrows drawn and drag-to-reschedule that runs the same engine as typing a date — one code path, tested to produce identical results either way. Also: cell-level comments, row attachments, conditional formatting rules, a card view grouped by a dropdown column, and a form that appends a row to the sheet from a public URL with a captcha or a token. Import and export: XLSX and CSV. The XLSX round trip must preserve hierarchy (as an indent level column) and predecessors (as a text column in the documented format) — losing the structure on export is what makes a project tool a dead end. Write tests for the forward and backward passes against a hand-computed network, for all four dependency types with negative lag, for cycle refusal, and for the XLSX round trip preserving indent levels. Do not build approvals, proofing, or connectors.